(I) Approval
of Indigenous Electrical Enclosure/ Equipment for use in
Hazardous Area
DGFASLI is the approving authority for granting approvals
to the flameproof enclosures being used in hazardous environment of the
factories covered by the Factories Act, 1948 as per IS: 2148-1981. DGFASLI is also granting approvals to other
electrical equipment like increased safety, intrinsically safe equipment, etc.
subject to the fulfillment of the requirements of the Code of practice IS 13408
(part I)-1992.
The procedure for granting approval is as under:
PROCEDURE FOR APPROVAL
- Equipment
has to be tested by approved testing laboratory as per the relevant
National Standards.
- The
following documents shall be submitted along with the proposal for
granting approval by the manufacturer.
(i)
Carbon Copy / next
original copy of test report from approved testing laboratory;
(ii)
Copy/ copies of drawing(s)
certified by an authority of the testing laboratory and duly attested by the
manufacturer (by senior level executive)
(iii)
Copy of the Chemical
composition analysis report, of light alloy metal used, such as LM4, LM6,
carried out in a Government approved testing laboratory. The chemical analysis report shall be of
the material used for the prototype and the copy of the same shall be duly
attested by the manufacturer (by senior level executive).
- For
gas Group II C enclosures in addition to the requirements at
Sl.No.1 & 2 above, the details of the users including address and
telephone number, to whom the equipment is being supplied shall be furnished.
- For
Supplementary / Addendum approval
in addition to the requirements at Sl.No.1 & 2 above, copies of
DGFASLI approval letters issued earlier shall be submitted.
- The
approval for gas Group II A and II B pro-type will be valid for a
period of five years (from the date of test report) after which it shall
require revalidation.
- The
test certificate issued by testing laboratory before 10 years from the
date of application shall not be considered as valid for granting
approval.
(II) Approval
of Electrical Enclosure/ Equipment manufactured and tested abroad for use in Hazardous
Area
Documents required for the scrutiny of the proposal:
- Verification
regarding standing of the company in the field manufacture of safety
equipment for use in hazardous areas
- Verification
of the code / standard/ specification followed and whether it is
comparable to corresponding Indian Standard Specification or any
acceptable international standards like IEC, EN, BS, UL, CSA, ANZ codes.
- Verification
of National Testing and Certifying Authority and its accreditation by the
Government authorities in the country of manufacture.
- Scrutiny
of the design drawing and verification of special conditions of
installation.
- Scrutiny
of the Test Report/ Approval Report of the equipment and its associated
components.
- Verification
of Listing Documents of the main as well as associated equipment and
accreditation of the Listing Authority by the Government Authorities in
the country of manufacture.
- List
of Industries where equipment have actually been put in to use in the
country of manufacture as well as in other countries.
- Particulars
of accreditation like ISO rating, etc. if any.
- Details
of Organisation and Indian representative who will entrusted with the job
of After Sales Service and Maintenance of the equipment.
- Copy
of C.C.O.E. approval letter if obtained already.
- Inspection
to the unit to check infrastructure, documents, Maintenance procedure,
instrument, etc.
(III) PROCEDURE FOR REVALIDATION OF APPROVAL
- The
manufacturer shall submit the proposal for revalidation atleast three
months before the expiry of the original approval along with the following
documents:-
(i)
The list of user, along
with their address and telephone numbers, to whom the equipment have been
supplied during the period of validity of approval;
(ii)
A certificate (on the
letter head) of the manufacturer that the equipment has / have not undergone
any change in its design during the period of validity and that the equipment
has / have been manufactured strictly in accordance with the drawing certified
by the testing laboratory and is/ are identical with the one tested and
certified by the testing laboratory.
(iii)
A copy of the valid BIS
licence duly attested by the manufacturer (by senior level executive);
(iv)
Copy/ Copies of the
approval(s) including permissible varioations, issued by DGFASLI, duly attested
by the manufacturer (by senior level executive).
- Further
revalidation of approval of such equipment after five years (i.e. 10 years
from the first approval) shall be issued after re-testing of the said
equipment by the approved testing laboratory. The procedure for approval shall be same as given in (A)
above.
(IV) OTHER IMPORTANT INFORMATION
- The
DGFASLI approval number and date must be inscribed in the nameplate of the
equipment
- Obtaining
licence from BIS, on approval from DGFASLI is mandatory.
- Approval
may be amended, reviewed or revoked, if considered necessary by the
DGFASLI. Any violation / deviation
observed in any manner shall result in revocation of the approval issued.
- Field performance
report from users of the Gas Group IIC equipment shall be furnished to the
DGFASLI for verification and record annually.
- Officials
of DGFASLI may visit the manufacturing unit as and when considered
necessary. The compliance report
on the suggestion/ observations made by them in their report shall be
submitted to DGFASLI within the time limit prescribed.